Repairs to flood damaged roads, bridges and causeways
We've assessed over 600 pieces of infrastructure damaged in the February 2022 floods including:
- Roads
- Bridges
- Causeways
- Guardrails.
The cost of repair and reconstruction works is more than $163 million.
The 600 pieces of infrastructure needing repair were bundled into 41 separate funding applications that were submitted to the State and Federal Governments.
We received funding for 200 of these damages.
We have now packaged these works into 19 projects by location and type of work. Read more about each project and timelines by selecting a page below.
- Main Arm Valley flood restoration works including Repair of Main Arm Road between Main Arm Upper Public School and Motts Road
- Left Bank Road works
- The Pocket Road
- Tristran Parade Landslip
- Coopers Lane Culvert
- Sherrys Bridge
- Mullumbimby Road
- Johnsons Road
- Wanganui Road
- Huonbrook Road Pack
- Upper Wilsons Creek
- Wilsons Creek Road
- Coopers Creek Road
- Area South Landslip works
- Beatties Creek
- Essential Public Assest Restoration (EPAR) 25
- Minor Landslips Pack
- Gravel Roads Pack
- Bridge Guardrail Pack