The Pocket Road Flood Restoration

  • Project typeEssential Public Asset Restoration (EPAR)
  • Project value$3,703,172.00
  • Project scheduleConstruction to commence mid to late 2026

We are repairing damage caused on The Pocket Road caused by the 2022 floods.

Works include 

  • Culverts 
  • Landslips 
  • Pavement works

Culverts 

Location  Description of works  Status 
Culvert near 826 The Pocket Road 
  • Replace headwall
  • Remove debris 
Planning to commence early 2026  
Culvert near 453 The Pocket Road
  • Reinstate erosion protection 
  • Remove debris
Planning to commence early 2026
Culvert near 209 The Pocket Road 
  • Remove debris 
  • Reinstate erosion protection 
Planning to commence early 2026
Culvert near 303 Middle Pocket Road 
  • Replace culvert
Planning to commence early 2026

Landslips

Location  Description of works  Status 

Landslip 2#

Near 1025 The Pocket Road

  • Remove excess material 
  • Revegetate the area 
  • Reshape upslope table drain 
Planning to commence early 2026

Landslip #3

Near 1025 The Pocket Road

  • Remove excess material
  • Revegetate the area
  • Reshape upslope table drain
Planning to commence early 2026

Landslip 1#

Near 1025 The Pocket Road

  • Remove excess material and vegetation 
  • Revegetate the area with hydro mulch 
  • Reshape upslope table drain 
Planning to commence early 2026

Road

Location Description of works  Status 
Sections of pavement 

Patching and shoulder reconstruction 

Planning to commence early 2026

 

Location

The pocket road, Byron Bay 2482  View Map

Google Map