Construction Schedule UpdateCurrent Daytime Works 7AM to 5PM dailyUpcoming Night Works: Starting Sunday 21 September, construction will resume during night hours 8PM to 5AMExpect short delays.
We are repairing various damages that occurred during the 2022 floods.
Works to restore the embankment located near 803 Wilsons Creek Road started in early June 2025.
This is a Design and Construct contract awarded to the contractor Quickway Constructions.
The remediation involves a combination of rockfill and a mass block retaining wall to support the failed embankment. TfNSW has approved to extend the wall a further 45m to allow for a safer road width.
Replacement of 55 culvert crossings along Wilsons Creek Road is now underway to improve drainage. Some of the works will be delivered as nightworks by Quickway Constructions.
Contractor Durack Civil have commenced construction work on a soil nail and shotcrete retaining wall to restore the failed embankment near 968 Wilsons Creek Road.
Site investigation and planning
Works commencing October 2025
Wilsons Creek additional Landslip 1 - Near 968 Wilsons Creek Road
Construction commenced.
Work commenced. Completion expected November 2025.