Left Bank Road flood restoration works

  • Project typeEssential Public Asset Restoration (EPAR)
  • Project value$5,645,563
  • Project scheduleCurrent to early 2026

We are repairing various damages that occurred on Left Bank Road and near Frasers Road, caused by the 2022 floods.

Works include

  • Road reconstruction in various parts of Left Bank Road. These works are now complete.
  • Repairs to landslides
  • Repairs to culverts and causeways.

Causeways and culverts

Location Description of work Status 
Left Bank Road - near 641 Left Bank Road, Mullumbimby Creek Install triple cell culvert and headwalls.

Construction early to mid 2026

Left Bank Road Causeway 4

 


  • Repair kerb
  • Remove debris from the creek.

Completed

Left Bank Road Causeway 3

  • Replace and repair concrete support
  • Debris removal. 
Completed
Left Bank Road Causeway 2 - near 698 Left Bank Road, Mullumbimby Creek
Install a new structure to replace existing.

Construction mid to late 2026

Landslides

Location Description of work  Current status and construction

Left Bank Road- near 599 Left Bank Road, Mullumbimby Creek

Major landslip

  • Install soil nail wall to help stabilize embankment.
  • Clear and remove debris
  • Install guardrails.
Completed 

 

 

Location

Left Bank Road - Various locations, Mullumbimby 2482  View Map

Google Map