Upper Wilsons Creek Road Flood Restoration Works

  • Project typeEssential Public Asset Restoration (EPAR)
  • Project value$5,273,986
  • Project scheduleProject complete September 2027

We are repairing various damages that occurred during the 2022 floods along Upper Wilsons Creek Road.

Works include

  • Landslips remediation
  • Road reconstructions
  • Culvert repairs and replacements
  • Debris removal
  • Causeway repairs
  • Low level bridges construction.

Causeway repairs

Location Description of work Status 
Causeway 1

Replace rock protection

Completed

 

Causeway 2
  • Repair kerbs
  • Remove flood debris (trees and branches)
Construction planned late 2025
Causeway 3
  • Replace low flow pipes with low level bridge
Construction starts late 2027
Causeway 4
  • Replace rock protection
  • Repair existing pipes and Northeast approach
Construction planned late 2025

 

 

Causeway 5
  • Reinstate downstream rock protection
  • Clear debris from blocked culvert
Construction starts late 2027
Causeway 6
 Replace with low level bridge Construction starts late 2027
Causeway 9

  • Remove large deposits of rock upstream and downstream which is disrupting flows
  • Replace rock protection around the low flow pipes
Construction planned late 2025

 

Causeway 15
Replace with box culvert Construction starts late 2027
Causeway 10
Minor repairs and debris removal from existing bridge
Construction starts late 2027
Causeway 12
Replace with low level bridge  Construction starts early 2027

Culverts & bridges

Location Description of work  Current status and construction

Culvert 2

Near the Threeways Cafe

  • Replace headwall
  • Remove silt
  • Rock protection
Completed

 

Culvert 3

Near 10 Huonbrook Road

 Replace outlet headwall Completed

 

Culvert 7  

Near 109 Upper Wilsons Creek Road

  • Replace 1 length of existing pipe and headwall
  • Remove excess sediment from swales 
  • Replace rock protection
Completed

 

Culvert 10

Near 1028 Upper Wilsons Creek Road

Remove debris, cleanout
Completed

Culvert 14

Near 246 Upper Wilsons Creek Road

Remove debris, rock protection
Construction starts early 2028

 

Culvert 18

Near 354 Upper Wilsons Creek Road

  • Replace pipes & headwalls
  • Reinstate downstream embankment
Construction starts early 2028

 

Culvert 24

Near 402 Upper Wilsons Creek Road

  • Clean outlet and inlet
  • Rock protection
Construction starts early 2028

Culvert 11

Near 132 Upper Wilsons Creek Road

Replace pipes and headwalls
Construction starts early 2028