The Sandhills Wetlands area was heavily sandmined in the 1960's, which destroyed the original wetlands.
For many years the Sandhills Estate, which is in the heart of Byron Bay, was overgrown and under-utilised, with a resulting increase in anti-social behaviour.
In 2020, Council developed a staged precinct plan for the Sandhills site.
This delivers the vision of the Byron Bay Masterplan, to provide a safe and accessible public spaces that combines ecological and cultural values with circulation routes and recreation activities.
Stages of the Sandhills Estate Precinct Plan
- Stage 1 – Tennyson Street upgrades to extend pedestrian/cycle paths from Suffolk Park to Sandhills Estate and provide some additional parking – completed in 2021
- Stage 2 – Cowper Street pedestrian pathway upgrades – to improve north/south access through Sandhills Estate - completed in 2021
- Stage 3 - New Middleton Street public toilets – completed in 2023
- Stage 4 - Gilmore Crescent upgrades that completed the pedestrian/cycle link from Suffolk Park, through Jarjumirr Park all the way to Main Beach, improved the road and created additional parking – completed in 2023
- Stage 5 – new Main Beach public toilets – completed in 2023
- Stage 6 – Jarjumirr Park skatepark and recreation precinct – completed in 2024
- Stage 7 – Middleton Street connection path – completed in 2024
- Stage 8 – the Sandhills Wetlands project and additional paths - underway.