| Landslip near 501 Binna Burra Road |
Remove failed slip material and replace with rockfill.
|
Construction likely to commence in early to mid 2026.
|
Landslip Near 506 Goonengerry Road
|
- Remove excess debris.
- Revegetate the area.
- Reinstate table drain.
|
Construction likely to commence in early to mid 2026.
|
Landslip Near 394 Kings Road
|
- Clear blocked culvert.
- Install gabion structure.
- Install guard rail.
|
Construction planned for early 2026.
|
| Landslip Near 180 Monet Drive |
- Construct gabion basket retaining wall.
|
Construction likely to commence in early to mid 2026.
|
| Landslip on Possum Shoot Road (approximately 400m from the intersection of Myocum Road) |
- Soil nail wall.
- Remove debris.
- Revegetate the area.
- Pavement repairs.
|
Construction planned for March 2026. |
Landslip near 345 St Helena Road
|
Install gravity retaining wall. |
Construction planned for mid 2026.
|