Broken Head Road - Reconstruction

Dates: 
10 October 2017 - 8 December 2017

UPDATE - 16/10/17
Works have been delayed due to inclement weather, works are planned to start this week (16/10 to 20/10) provided there is a sufficient window of dry weather.   Please note these works will not involve the removal of any trees.
______________________________________________________________________________

UPDATE - 11/10/17
Works have been delayed due to inclement weather, start date to be confirmed.   Please note these works will not involve the removal of any trees.
______________________________________________________________________________
Byron Shire Council wishes to advise that they will be undertaking Road Reconstruction Works commencing on Monday 10 October 2017 extending for a 6 week period to 21 November 2017, weather permitting.  Work hours will be 7am to 6pm Monday to Friday.

The 600m work zone is on Broken Head Road from the turning/merge lanes at Broken Head Hall north to Bryon Bay.  The zone will also include the intersection and approach on Midgen Flat Road.

Major construction works to be undertaken in two stages as per the staging diagram on opposite page.

Stage One

  • Removal of existing wearing surface, reshaping, compacting and sealing.
  • The seal will require 1 week of curing prior to placement of Asphalt.

Stage Two

  • Asphalt works - will require up to 2 weeks for placement, weather permitting.

Council is mindful of upcoming HSC exams and has programmed works to reduce impact students and parents during exam weeks.

The worksite will be under Traffic Control and motorists are reminded to obey all instructions.  Additional advice regarding the project and wet weather delays will be available on Councils webpage.  Council apologises for any inconvenience caused by these essential works and asks for your patience.

Should you require any other general information about the project please feel free to contact Council's Works Engineer on 6685 9300.